Radiological and conventional safety monitoring plan

Radiological and conventional safety monitoring plan

The Thermal Maintenance Agency (AMT) of EDF has commissioned CERAP Prévention to implement the radiological and conventional safety monitoring plan across the national fleet of nuclear power plants.

34 worksites 20000 measurements 700 field visits and safety talks
CERAP Prévention
X

Description

Key objectives

  • Achieve zero safety or contamination incidents during maintenance operations

  • Optimise collective dose management and its distribution

  • Anticipate and plan logistics prior to interventions

 

Our approach

  • Logistical verification: pre-job inspections and preparation tours

  • Dosimetry control: implementation of optimisation and radiation protection measures

  • Prevention coordination: safety briefings, on-site supervision and experience feedback

 

CERAP Prévention added value

  • Improved behaviours and strengthened safety culture among field teams

  • Capitalisation of events and creation of a dedicated knowledge library

  • Continuous reduction of frequency and severity rates (TF/TG) and overall collective dose

  • Comprehensive feedback (REX) on radiological issues related to valve replacement work in controlled areas

Similar projects

Design of an underwater measurement system
Characterisation Nuclear Measurement Engineering
CERAP Prévention
X
Design of an underwater measurement system
A trusted partner for high-quality spectrometry solutions, CERAP Prévention designed for Laborelec a waste characterisation system for use in a storage pool, following a series of successful projects completed for Electrabel and EDF.
Operation of an environmental chemistry laboratory
environmental chemistry laboratory
CERAP Prévention
X
Operation of an environmental chemistry laboratory
The CEA Cadarache site has entrusted CERAP Prévention with the operation of its environmental chemistry laboratory.Working on the water cycle, we contribute to ensuring the cleanliness and compliance of liquid discharges into the natural environment.
Prevention Plan Unit – Gravelines Power Plant
1516 on-site safety visits during outages – per year 1589 on-site safety visits during maintenance periods – per year 1189 site inspections on major projects
CERAP Prévention
X
Prevention Plan Unit – Gravelines Power Plant
The Gravelines Nuclear Power Plant (CNPE) commissioned CERAP Prévention to manage the Prevention Plan Unit, ensuring real-time administrative updates and a strong on-site presence.